PAARK HABEEB is a residential apartment project in BUDVEL, Ranga Reddy district; the mandal is not disclosed in the project identity record. It is being developed by PAARK BUILDERS, a partnership. The project covers 598.57 sq m and comprises 1 building with 1 Stilt + 5 upper floors and 15 apartments: 5 2BHK and 10 3BHK. Its TG-RERA registration number is P02400001372, and the original completion undertaking gives 31.12.2020.

📍 See this location on the map
Budvel, Ranga Reddy · geocoded — approximate.

1. Project at a glance

Project identity

ItemProject record
Registered namePAARK HABEEB RERA record
Project typeResidential apartment project RERA record RERA filing
Phase / registered portionPhase not separately identified in the supplied registration record. The registered land is identified as Survey No. 159/1, Plots 44 & 45. Land records
TG-RERA registrationP02400001372; certificate issued 11/11/2019. RERA record
Registration validity11/11/2019–31/12/2020; the supplied certificate records no extension. Registration validity is distinct from the completion undertaking and from occupancy-certificate status. RERA record
Registered promoterPAARK BUILDERS, a partnership. RERA record Corporate record
RERA status in supplied recordRegistration certificate issued; stated validity ended 31/12/2020. Current registration status is not established by the supplied record.

Land and geographic identity

ItemProject record
Locality / revenue villageBUDVEL / Budvel Village RERA record Land records
MandalNot disclosed in the project identity record. Land records
DistrictRanga Reddy RERA record Land records
PIN500030 RERA record RERA filing
Project survey number and subdivisionSurvey No. 159/1 RERA record Land records
Plot identifiers44 & 45 RERA filing
Registered site extent598.57 sq m in the RERA land details. RERA filing
Total / net area598.57 sq m total and 598.57 sq m net in the RERA land details. RERA filing
BoundariesEast: PLOT NO 46; West: OTHERS PHASE I; North: OTHERS PHASE I; South: ROAD WIDTH 12. RERA filing

Development identity

ItemProject record
Sanctioning authorityGreater Hyderabad Municipal Corporation (GHMC) Approvals record
Principal building approvalApproval No. 2/C11/07129/2019, dated 06 May, 2019. Approvals record
Other approval reference on permitFile No. 2/CH/00441/2019; Layout / Sub Divn. No. 122/MP2/H/98.
Approved built-up area1826.82 sq m in the RERA project fields. RERA filing
Building count1 building/unit in the project filing; the GHMC permit describes one residential building. RERA filing
Sanctioned configuration1 Stilt + 5 upper floors; printed height 15 m.
Parking levels / countStilt is identified in the sanctioned configuration; a sanctioned parking-space count and allocation are not established in the supplied records. RERA filing
Approved versus RERA-declared unitsThe RERA land details state 1 total building unit and 1 proposed building unit; the unit schedule lists 15 apartments (10 3BHK and 5 2BHK). A separate sanctioned apartment-count figure is not provided in the supplied permit extraction. RERA filing RERA unit table

Offering and status

ItemProject record
RERA-filed configurations2BHK: 5 units; 3BHK: 10 units. RERA unit table
RERA-filed saleable area2BHK: 109.7 sq m; 3BHK: 113.35 sq m. RERA unit table
Booked / availableThe TG-RERA portal values supplied show 0 booked / 5 available for 2BHK and 0 booked / 10 available for 3BHK. These counts are indicative: the record supplies no as-of date. RERA unit table
Construction stageNo independently verified site-progress or completion-stage record is supplied. The RERA amenity schedule records some items at 100% and others at 0%; these are filed progress entries, not independent site verification. RERA amenities
Original completion undertaking31.12.2020, declared in Form B by Mohammed Moinuddin.
Revised completion dateNo revised date is established in the supplied evidence.
Occupancy / completion certificateNo occupancy or completion certificate is supplied; status is not established. Document index

2. The project story

PAARK HABEEB is a RERA-registered residential apartment project associated with Plots 44 and 45 in Survey No. 159/1, Budvel Village, Ranga Reddy district. Its GHMC building permit describes one residential building with a stilt level and five upper floors. The RERA unit schedule records 15 apartments: ten 3BHK and five 2BHK. RERA record Land records RERA unit table

The project’s registration certificate records validity through 31/12/2020, while the promoter’s Form B undertaking gives the same date as the intended completion deadline. Those dates do not establish that construction was completed by then or that an occupancy certificate was issued. Neither current on-site progress nor an occupancy/completion certificate is established by the supplied evidence. Document index

3. Master plan, architecture & building design

The GHMC building permit identifies a single residential building, 1 Stilt + 5 upper floors, with a printed height of 15 m and site area of 595.99 m². It also records setbacks of Front 3.02, Side I 3.51 and Side II 4.5; the supplied extraction does not state the units for these setback figures.

The RERA filing lists 1826.82 sq m as approved built-up area. The supplied building-permit extraction also includes the figures 1,453.95 and 276.99, but their labels are not sufficiently clear in the extracted record to assign them confidently to a specific area measure. No floor-by-floor arrangement, building footprint, flats per floor, lift or stair details, entry/exit arrangement, or phase-wise building plan is established in the supplied materials. RERA filing

The site is described in the filing as 598.57 sq m total and net area. The permit extraction separately states a site area of 595.99 m² and net area of 595.99 m². The meaning and relationship of the permit’s area fields are not resolved here. The filing and available plan extraction do not establish a residential/commercial split, internal-road network, or quantified open-space allocation. RERA filing

4. Homes, configurations & floor plans

ConfigurationUnitsBookedAvailableRERA saleable areaMeasured carpet areaLoading (if supplied)
2BHK505109.7 sq m52.5–60.9 sq m; median 56.7 sq m (software-measured)48%
3BHK10010113.35 sq m80.1–95.1 sq m; median 87.2 sq m (software-measured)23%

RERA unit counts, availability and saleable areas are from the filing; booking figures have no supplied as-of date and should be treated as indicative. The carpet-area ranges and loading figures are software measurements from the supplied floor-plan drawing record, not RERA-filed carpet-area disclosures; the drawing-based measurements are flagged as needing review. The record explains that saleable area includes the home’s share of common areas, while carpet area is measured from drawing geometry. RERA unit table Floor plans RERA unit details

The measured 2BHK design sample includes a hall, kitchen, two bedrooms and two toilets. The sample 3BHK plan includes a drawing room, three bedrooms, a kitchen, two toilets, a foyer and wash areas. These descriptions are from the measured plan samples and do not establish that every unit has identical dimensions or layout. RERA unit details

5. Parking & vehicle circulation

The building permit identifies a stilt level, but the supplied sanctioned-plan extraction does not establish a parking-space count, vehicle circulation layout, ramp, separate visitor or accessible parking provision, or EV charging. The RERA project fields record a mortgage area of 151.81 sq m, not a parking count or unit allocation. RERA filing

The vendor-supplied material lists covered car parking, open car parking, closed car parking and dedicated bike parking; these are vendor-reported features, not confirmation of sanctioned quantities, delivery, or exclusive allocation to a particular apartment. No legally documented parking allocation for individual units is established in the supplied evidence. Promoter website

6. Amenities, recreation & open spaces

The RERA amenity schedule gives the following entries. Percentages are the progress values recorded in that schedule; they are not independent verification of completion. RERA amenities

FacilityDescription / sizeEvidence sourceDeclared progress / verified status
Internal Roads & FootpathsNo size statedRERA amenity schedule0%; not independently verified
Water SupplyNo source, capacity or size statedRERA amenity scheduleYES; 100%; not independently verified
Sewerage (Chamber, Lines, Septic Tank, STP)No system capacity statedRERA amenity schedule0%; not independently verified
Storm Water DrainsNo size statedRERA amenity schedule0%; not independently verified
Green Strip/TOT LOT/ParkNo area statedRERA amenity scheduleYES; 100%; not independently verified
Street LightingNo quantity statedRERA amenity schedule0%; not independently verified
Community BuildingsNo description or size statedRERA amenity schedule0%; not independently verified
Treatment and Disposal of Sewage and Sullage WaterNo capacity statedRERA amenity schedule0%; not independently verified
Solid Waste Management and DisposalNo system details statedRERA amenity schedule0%; not independently verified
Water Conservation, Rain Water HarvestingNo capacity statedRERA amenity schedule; GHMC permit also lists RWHPS without a countYES; 100% in RERA schedule; not independently verified
Energy managementNo details statedRERA amenity schedule0%; not independently verified
Fire Protection and Fire Safety RequirementsNo system details statedRERA amenity schedule0%; not independently verified
Electrical Meter Room, Sub-Station, Receiving StationNo capacity statedRERA amenity scheduleYES; 100%; not independently verified
Aggregate area of recreational Open SpaceNo area statedRERA amenity schedule0%; not independently verified

The vendor also lists a clubhouse, swimming pool, gym, children’s play area, waste management, security and water-related features. These are vendor-reported claims; the supplied RERA amenity schedule does not establish those individual facilities as sanctioned or completed. Promoter website RERA amenities

7. Utilities, building services & safety

The RERA schedule records Water Supply as YES at 100%, Water Conservation, Rain water Harvesting as YES at 100%, and Electrical Meter Room, Sub-Station, Receiving Station as YES at 100%. The GHMC permit extraction lists “No. of RWHPS” without a count. These are filed/sanction-record entries; the evidence does not provide water sources or storage capacity, rainwater-system capacity, electrical capacity, or independent completion verification. RERA amenities

The RERA schedule records sewerage, storm-water drains, sewage/sullage treatment, solid-waste management, energy management and fire-protection/fire-safety requirements at 0%. The supplied evidence does not establish STP capacity, reuse arrangements, drainage design, backup power, lift details, fire-system specifications, security systems, or accessibility provisions. RERA amenities Document index Promoter website

8. Location, access & connectivity

The registered project location is BUDVEL, Budvel Village, Ranga Reddy district, PIN 500030, on Plots 44 & 45, Survey No. 159/1. The project boundary record identifies a ROAD WIDTH 12 on the south; it does not name that road. RERA record Land records RERA filing

The supplied location data gives these distances: Financial District (Nanakramguda) 1.2 km; IndusInd Bank 0.4 km; unnamed bus station 2.2 km; Manuu Polytechnic Hyderabad 1.6 km; Sankaraya Eye Hospital 1.6 km; ADP 0.0 km; South india shopping mall 2.6 km; unnamed park 1.2 km; and Nanakramguda Govt primary school 0.5 km. These are supplied location-record distances; no travel times or transit-service details are provided. Location record

9. Developer & development status

The registered promoter is PAARK BUILDERS, identified in the project record as a partnership. The listed partners are AMTUL AKBAR and MARIAM SAHER; MOHAMMED MOINUDDIN is identified as authorized signatory. The supplied corporate record does not establish a corporate identification number or a verified registered-office address. Corporate record Parties record

Mohammed Moinuddin’s Form B declaration identifies him as promoter and undertakes completion by 31.12.2020. The registration certificate records validity through that date and no extension in the supplied certificate extraction. No reliable project-specific construction-progress update or occupancy/completion certificate is supplied, so present physical completion and handover status remain unestablished. Document index

10. Approvals, official records & documents

TG-RERA registration certificate
Available evidenceP02400001372, Form C; issued 11/11/2019, valid through 31/12/2020.
Scope / notePAARK HABEEB; certificate extraction records no extension.
GHMC building permit
Available evidenceApproval No. 2/C11/07129/2019; dated 06 May, 2019; File No. 2/CH/00441/2019.
Scope / notePermit extraction describes one building at Survey No. 159/1, 1 Stilt + 5 upper floors.
Layout / Sub Divn. reference
Available evidence122/MP2/H/98.
Scope / noteListed as an additional reference on the building permit; a separate stamped layout approval is not established by the supplied extraction.
Form B declaration
Available evidenceDeclaration by Mohammed Moinuddin, dated 20.08 day of 2019.
Scope / noteIncludes the promoter’s completion undertaking and other declarations.
Layout plan document
Available evidenceDocument 67134, listed as layout plan; extraction is not available. Document index
Scope / noteDrawing-derived unit measurements are supplied separately and identified as software-measured.
Occupancy / completion certificate
Available evidenceNot supplied in the reviewed documents. Document index
Scope / noteIssuance and current status are not established.

Due-diligence summary

Risk & red flags

1 high
  • Completion date has passed and the project is not complete
Full details: coming soon

Land & title

Nothing confirmed
  • Land record and title documents checked.
  • Nothing confirmed found in records checked.
Searched: Bhu Bharati land record, IGRS registration records, title documents
Full details: coming soon

Approvals

On file
  • plan approval 2/C11/07129/2019 in the RERA filing.
Searched: RERA filing, HMDA/DTCP/GHMC approvals
Full details: coming soon

Legal

Searched
  • Court and regulator records searched for this project.
  • No TG-RERA proceedings found.
Searched: eCourts, High Court, consumer forums, TG-RERA orders
Full details: coming soon

Contacts

  • Promoter: PAARK BUILDERS (RERA filing).
  • Architect, engineer and other filed contacts in the full file.
Full details: coming soon

Frequently asked questions

Is PAARK HABEEB registered with Telangana RERA?

Yes. PAARK HABEEB is registered with the Telangana Real Estate Regulatory Authority as P02400001372; the registration status is New Project.

Who is the developer of PAARK HABEEB?

The promoter named in the RERA registration is PAARK BUILDERS.

Where is PAARK HABEEB located?

PAARK HABEEB is in BUDVEL, Rangareddy, Telangana (500030).

When will PAARK HABEEB be completed?

The promoter's proposed date of completion filed with RERA is 31/12/2020. This is the promoter's declaration, not a guarantee.