Udaya Cresent
UDAYA CRESENT is a residential apartment project in Kondapur, Serilingampally mandal, Ranga Reddy district, developed by registered promoter Creative Koven Developers LLP. The project covers 16,389.77 sq m and comprises four residential blocks, A–D, each Ground +7 floors, and one amenities block stated as Cellar, Ground +3 Upper floors. The TG-RERA filing records 250 3BHK apartments, each with a saleable area of 211.21 sq m. Its TG-RERA registration is P02400000425, and the proposed completion date is 04/11/2023.
More from Creative Koven Developers LLP · 2 projects →
At a glance
- RERA registration
- P02400000425
- Registration valid
- 12/03/2019 to 04/11/2023; the certificate states four years. The supplied certificate records no extension
- Promoter
- Creative Koven Developers LLP
- Site area
- 16,389.77 sq m
- Building permit
- Hyderabad Municipal Corporation in the filed building permit; project record identifies GHMC as authority
- Saleable area
- 211.21 sq m per unit
- Construction stage
- Project record declares 90% completeness; this is a filed declaration, not an independent site inspection
- Occupancy certificate
- No project OC or completion certificate is included in the supplied evidence; status is therefore not verified
The full project file
Description
Udaya Cresent is a residential apartment project with 250 units across four towers, each with eight floors, on 16,389.77 sq m of land. Its TG-RERA filing records the project as ongoing, with a proposed completion date of 4 November 2023.
- Project type
- Residential (apartment)RERA filing
- Units
- 250RERA filing
- Towers
- 4RERA filing
- Floors
- 8RERA filing
- Land area
- 16389.77 sq mRERA filing
- Possession
- 04/11/2023RERA filing
- Status
- On-Going ProjectRERA filing
Gallery


Configurations & sizes
The approved floor-plan drawings have not yet yielded a measured carpet-area figure for the 3BHK configuration. The TG-RERA filing records 250 units, zero bookings and a saleable area of 211.21 sq m.
| Type | Saleable | Source |
|---|---|---|
| 3BHK | 211.21 sq m | RERA filing |
Amenities
The filing lists park and community-building amenities alongside basic project infrastructure.
- Green Strip/TOT LOT/Park
- Community Buildings
Location & connectivity
The project is in Kondapur, Serilingampally mandal, Ranga Reddy district, PIN 500084.
Promoter
The promoter is CREATIVE KOVEN DEVELOPERS LLP, a limited liability partnership with one other registered project. Its official website is creativekoven.com; the named architect is BASITH ALI and the structural engineer is E VISWANATH REDDY.
Sources & web results
- Creative Udaya Cresent Kondapur, Hyderabad99acres.com
- Creative Koven Udaya Cresent RERA Detailssquareyards.com
- UDAYA CRESENT Ranga Reddyaurumproptech.in
- Creative Koven Udaya Cresent in Kondapur, Hyderabadmagicbricks.com
- UDAYA CRESENT (Telangana) Report & Status | Real Estate Reportsrealestatereports.in
- 172 - 3 BHK Flats for rent in Udaya Cresent, Hyderabadnobroker.in
Public RERA registration record
Telangana RERA, as filed by the promoter.
- Registered name
- UDAYA CRESENT
- Developer / Promoter
- CREATIVE KOVEN DEVELOPERS LLP
- Project type
- Residential
- RERA Registration No.
- P02400000425
- Registration Status
- On-Going Project
- Proposed completion
- 04/11/2023
- Approving authority
- GHMC
- Plan approval no.
- 53376/HO/WZ/Cir-11/2016
- Total site area
- 16,390 sq m (4.1 acres)
- Approved built-up area
- 47,183 sq m (11.7 acres)
- Buildings (approved plan)
- 5
- Locality
- Kondapur
- Mandal
- Serilingampally
- District
- Rangareddy
- PIN code
- 500084
- Documents on File
- 37
Frequently asked questions
Is UDAYA CRESENT registered with Telangana RERA?
Yes. UDAYA CRESENT is registered with the Telangana Real Estate Regulatory Authority as P02400000425; the registration status is On-Going Project.
Who is the developer of UDAYA CRESENT?
The promoter named in the RERA registration is CREATIVE KOVEN DEVELOPERS LLP.
Where is UDAYA CRESENT located?
UDAYA CRESENT is in Kondapur, Serilingampally, Rangareddy, Telangana (500084).
When will UDAYA CRESENT be completed?
The promoter's proposed date of completion filed with RERA is 04/11/2023. This is the promoter's declaration, not a guarantee.