Manikanta Smart City
MANIKANTA SMART CITY is a plotted residential layout in Kudakuda, Chivemla Mandal, Suryapet District. The registered promoter is GORUGANTI RAVINDAR RAO & OTHERS, described as joint developers. The RERA-recorded site area is 68,605.35 sq.m, and the tentative layout provides for 226 plots; plot configurations are not stated in the RERA record. The project is registered under TG-RERA number P01900006206, with proposed completion on 18/08/2024.
At a glance
- RERA registration
- P01900006206, granted under section 5; certificate issued 29/04/2023.
- Registration valid
- 29/04/2023–18/08/2024; no extension is recorded in the supplied certificate. Registration validity is distinct from completion and occupancy status.
- Promoter
- GORUGANTI RAVINDAR RAO & OTHERS, described in the filing as joint developers; legal entity type is recorded as “Others,” with description “JOINT DEVELOPERS.”
- Site area
- 68,605.35 sq.m in the RERA land details.
- Building permit
- Suryapet Municipality/Municipal Corporation; the RERA record lists DTCP as the authority name.
- Construction stage
- RERA amenity fields report several infrastructure items at 80%; these are reported progress figures, not independent site verification.
- Occupancy certificate
- Not supplied. The project is a plotted layout; no project completion or occupancy certificate is evidenced in the supplied material.
The full project file
Description
Manikanta Smart City is a plotted development registered as a new project with TG-RERA. The filing records a land area of 68,605.35 sq m and a proposed completion date of 18 August 2024.
- Project type
- Plotted DevelopmentRERA filing
- Land area
- 68605.35 sq mRERA filing
- Possession
- 18/08/2024RERA filing
- Status
- New ProjectRERA filing
Configurations & sizes
This is a plotted development; plot sizes measured from the approved layout drawings range from 114.78 to 288.85 sq m and should be verified. TG-RERA unit, booking and saleable-area figures are not disclosed.
Amenities
The project disclosures describe parks, a bore and open parking, alongside infrastructure for roads, water, sewerage, drainage, lighting and rainwater harvesting.
- Green Strip/TOT LOT/Park
- Bore
- Open Parking
Specifications
- Status
- Completed
Location & connectivity
The project is in Kudakuda, Chivemla mandal, Suryapet district, Telangana 508213.
Promoter
The promoter is GORUGANTI RAVINDAR RAO & OTHERS, listed as an “Others” entity. The count of its other registered projects and an official website are not disclosed; the filing names SYED ZAMEER HASAN as architect and PRASHANTH KUMAR L as structural engineer.
Sources & web results
- Manikanta Smart City Kudakuda, Suryapet99acres.com
- MANIKANTA SMART CITY | undefined | Kudakuda | Photos & ...bhumiboss.com
- Manikanta Smart City FAQs - Kudakuda, Suryapet99acres.com
- MANIKANTA SMART CITY (Telangana) Report & Status | Real ...realestatereports.in
- MANIKANTA SMART CITY Suryapet – RERA No. ...aurumproptech.in
Public RERA registration record
Telangana RERA, as filed by the promoter.
- Registered name
- MANIKANTA SMART CITY
- Developer / Promoter
- GORUGANTI RAVINDAR RAO & OTHERS
- Project type
- Plotted Development
- RERA Registration No.
- P01900006206
- Registration Status
- New Project
- Approved on
- 18/08/2022
- Proposed completion
- 18/08/2024
- Approving authority
- DTCP
- Total site area
- 68,605 sq m (17.0 acres)
- Approved built-up area
- 40,508 sq m (10.0 acres)
- Locality
- Kudakuda, Kudakuda
- Mandal
- Chivemla
- District
- Suryapet
- PIN code
- 508213
- Documents on File
- 31
Frequently asked questions
Is MANIKANTA SMART CITY registered with Telangana RERA?
Yes. MANIKANTA SMART CITY is registered with the Telangana Real Estate Regulatory Authority as P01900006206; the registration status is New Project.
Who is the developer of MANIKANTA SMART CITY?
The promoter named in the RERA registration is GORUGANTI RAVINDAR RAO & OTHERS.
Where is MANIKANTA SMART CITY located?
MANIKANTA SMART CITY is in Kudakuda, Chivemla, Suryapet, Telangana (508213).
When will MANIKANTA SMART CITY be completed?
The promoter's proposed date of completion filed with RERA is 18/08/2024. This is the promoter's declaration, not a guarantee.