Kinetic Infra
KINETIC INFRA is a residential apartment project in Madhava Hills, Serilingampally mandal, Ranga Reddy District, developed by the registered promoter Kinetic Infra. It covers 510.30 sq.m. and comprises one Stilt + 5 residential building with 10 3BHK homes. The project is registered under TG-RERA number P02400000781, with proposed completion on 27/10/2024.
More from Kinetic Infra · 2 projects →
At a glance
- RERA registration
- P02400000781; Form C registration issued 25/05/2019, valid through 27/10/2024; certificate says it may be extended by the Authority in accordance with the Act and Rules
- Promoter
- Kinetic Infra
- Site area
- 510.30 sq.m. in the GHMC plan; net area also stated as 510.30 sq.m.
- Building permit
- Greater Hyderabad Municipal Corporation (GHMC)
- Saleable area
- 136.5 sq.m. per unit
- Booked / available
- 0 booked; 10 available in the portal data supplied. The portal record has no as-of date, so counts are indicative rather than a current availability confirmation
- Construction stage
- The RERA header records 80% completeness, but no as-of date or independent site inspection is supplied; this is not an independently verified construction update
- Occupancy certificate
- No OC or completion certificate is included in the supplied project documents; status is not established
The full project file
Description
The TG-RERA filing describes a residential apartment project on 510.3 sq m of land, with 10 units in one tower across five floors. Its recorded status is New Project, with proposed completion on 27 October 2024.
- Project type
- Residential (apartment)RERA filing
- Units
- 10RERA filing
- Towers
- 1RERA filing
- Floors
- 5RERA filing
- Land area
- 510.3 sq mRERA filing
- Possession
- 27/10/2024RERA filing
- Status
- New ProjectRERA filing
Configurations & sizes
The 3BHK carpet area measures 92.8–94.7 sq m from the approved floor-plan drawings; this is a drawing-based measurement, not a RERA disclosure, and should be verified against the drawings. The TG-RERA filing records 10 units, 0 booked, and a saleable area of 136.5 sq m.
| Type | Saleable | Source |
|---|---|---|
| 3BHK | 136.5 sq m | RERA filing |
Amenities
The filing lists recreational open-space and park-related provisions, alongside infrastructure provisions.
- Green Strip/TOT LOT/Park
- Aggregate area of recreational Open Space
Location & connectivity
The project is in Madhava Hills, Ranga Reddy district, at PIN 500084.
Promoter
Kinetic Infra is a partnership, and its official website is kineticinfra.in. The promoter has one other registered project; the filing names Rajitha Kalwapally as architect and Vakkalagadda Venkata Charan as structural engineer.
Sources & web results
- Kinetic Celestia B Serilingampally, North Hyderabad, Hyderabadbigestate.io
- KINETIC INFRA (Telangana) Report & Status | Real Estate Reportsrealestatereports.in
- housing.com
- Kinetic Celestia B in Serilingampally, Hyderabadhousing.com
- KINETIC INFRA Hyderabad – RERA No. P02400000445aurumproptech.in
- Kinetic Celestia in Serilingampally, Hyderabadhousing.com
Public RERA registration record
Telangana RERA, as filed by the promoter.
- Registered name
- KINETIC INFRA
- Developer / Promoter
- Kinetic Infra
- Project type
- Residential
- RERA Registration No.
- P02400000781
- Registration Status
- New Project
- Approved on
- 27/10/2018
- Proposed completion
- 27/10/2024
- Total site area
- 510 sq m (0.1 acres)
- Approved built-up area
- 1,417 sq m (0.4 acres)
- Buildings (approved plan)
- 1
- Locality
- MADHAVA HILLS
- District
- Rangareddy
- PIN code
- 500084
- Documents on File
- 7
Other registrations of Kinetic Infra
Frequently asked questions
Is KINETIC INFRA registered with Telangana RERA?
Yes. KINETIC INFRA is registered with the Telangana Real Estate Regulatory Authority as P02400000781; the registration status is New Project.
Who is the developer of KINETIC INFRA?
The promoter named in the RERA registration is Kinetic Infra.
Where is KINETIC INFRA located?
KINETIC INFRA is in MADHAVA HILLS, Rangareddy, Telangana (500084).
When will KINETIC INFRA be completed?
The promoter's proposed date of completion filed with RERA is 27/10/2024. This is the promoter's declaration, not a guarantee.