Risk & red flags
- Completion date has passed and the project is not complete
JP DEVELOPERS · Rangareddy · RERA P02400001495
Panchavati is a plotted development in Burgupally Gram Panchyat, Machanpally (M), Ranga Reddy district, developed by the registered promoter JP DEVELOPERS. The project filing states a total land area of 103842.34 sq.mts, affected area of 1456.87 sq.mts and net area of 102385.47 sq.mts; the draft layout approval provides for 261 plots. The TG-RERA registration is P02400001495, and the proposed completion date is 02/11/2020.
Project identity
| Field | Project record |
|---|---|
| Registered project name | Panchavati |
| Project type | Plotted development / plotted layout RERA filing |
| Phase / registered portion | Phase not separately identified; TG-RERA registration is for Panchavati |
| TG-RERA registration | P02400001495; issued 27/12/2019 and valid through 02/11/2020. The certificate records no extension |
| Registered promoter | JP DEVELOPERS (certificate styling: “Jp Developers”); partnership RERA record RERA filing Parties record |
| RERA status in supplied record | Registration certificate issued; its stated validity period has ended. Current registration status is not established by the supplied record |
Land and geographic identity
| Field | Project record |
|---|---|
| Locality / revenue village | Burgupally Gram Panchyat in the RERA filing; the layout approval identifies Burgupally village and Burgupally Gram Panchayat RERA record RERA filing |
| Mandal | Not disclosed in the RERA identity fields. The layout approval names Machanpally (M) Land records |
| District | Ranga Reddy in the RERA project record; the layout approval states Vikarabad District RERA record |
| PIN | 501101 in the project header and registration certificate RERA record |
| Survey numbers / subdivisions | 24/A, 24/AA, 24E, 25A, 25AA and 25E in the RERA project record; the layout approval writes these as 24/A, 24/AA, 24/E, 25/A, 25/AA and 25/E RERA record Land records |
| Site extent in project filing | Total 103842.34 sq.mts; affected area 1456.87 sq.mts; net area 102385.47 sq.mts RERA filing |
| Extent stated in layout approval | Total layout area Ac. 25.66 Cents; 124194.40 Sq. Yds.; net layout area Ac. 25.30 Cents; 122452.00.Sq. Yds |
| Boundaries recorded in project filing | East: Nala and Neighbours Land; West: Railway Track; North: Land belongs to Harsha Vardhan Reddy and Others; South: Land belongs to Patti Prakasham RERA filing |
Development identity
| Field | Project record |
|---|---|
| Sanctioning authority | Director of Town and Country Planning; approval delegated to Burgupally Gram Panchayat |
| Principal layout approval | Draft-TLP.No.111/2018/H; approval letter number Lr.Roc.No. 3242/2018/H, dated as printed 2--11-2018 |
| RERA-filed plan reference | TLP.No.111/201/H RERA record RERA filing |
| Approved layout scale | 261 plots in the draft layout approval |
| Land-use split stated in draft approval | Total layout area Ac. 25.66 Cents; 124194.40 Sq. Yds.; Nala Area Ac. 0.36Cents; 1742.40 Sq Yds.; Net Layout Area Ac. 25.30 Cents; 122452.00.Sq. Yds; open space Ac. 2.53 Cents; 12245.20 Sq. Yds (10.00 %); road area Ac. 6.86 Cents; 33202.40 Sq. Yds. (26.73 %); plotted area Ac. 16.234 Cents; 78572.56 Sq. Yds (63.27 %); mortgage area Ac.2.44 Cents; 11809.60 Sq. Yds. (15.03 %) |
| Approved built-up area / buildings and floors | Not applicable to the filed plotted-layout description; no building count, floor configuration or approved building built-up area is supplied for this layout RERA filing |
Offering and status
| Field | Project record |
|---|---|
| RERA-identified offering | Plots; the project’s RERA filing identifies a plotted development RERA filing |
| Plot count | 261 plots in the draft layout approval |
| RERA-filed plot size range / inventory | Not supplied in the available RERA project data |
| Marketing-described plot size | “plot 1800 - 3600 sq.ft (167.23 - 334.45 sq.m)”—a vendor/third-party listing, not a RERA-filed figure Promoter website |
| Construction / development stage | RERA amenity entries report water supply, green strip/park, street lighting and rainwater harvesting at 10%, 10%, 10% and 15%, respectively; several other listed infrastructure items are shown at 0%. These are filed progress figures, not an independent site inspection RERA amenities |
| Completion deadline | RERA header gives proposed completion 02/11/2020; the registration certificate was valid through the same date RERA record |
| Occupancy / completion certificate | No occupancy or completion certificate is present in the supplied project documents. The plotted-layout approval calls for completion of required works and final layout approval Document index |
Panchavati is registered as a plotted-development project by JP DEVELOPERS, covering the survey subdivisions 24/A, 24/AA, 24E, 25A, 25AA and 25E. The filed project details identify Burgupally Gram Panchyat, Ranga Reddy district and PIN 501101; the draft layout approval describes the site as Burgupally village under Machanpally (M). RERA record RERA filing
The layout approval describes a scheme of 261 plots, with land allocated to plotted area, roads, open space, a nala area and plots reserved as mortgage security to the Gram Panchayat. Its conditions require development works and a subsequent final layout approval; the document expressly says permission to develop the land is not proof of title.
The RERA registration certificate ran from 27/12/2019 to 02/11/2020 and records no extension. The supplied record does not establish the current on-site condition, whether all layout works are complete, whether final layout approval was issued, or whether a completion certificate was obtained. The percentages entered for selected infrastructure components are promoter-filed progress information, not independently verified construction progress. RERA amenities
This is a plotted layout, not a building or apartment scheme in the supplied project record. The RERA-filed land details state total area 103842.34 sq.mts, affected area 1456.87 sq.mts, and net area 102385.47 sq.mts. The draft layout approval separately describes total and net layout extents in acres and square yards. RERA filing
The draft approval allocates 10.00 % of the layout to open space, 26.73 % to roads and 63.27 % to plotted area. It also identifies Ac. 0.36Cents; 1742.40 Sq Yds. as Nala Area and Ac.2.44 Cents; 11809.60 Sq. Yds. as mortgage area. Plots 135 TO 174 are specified for mortgage to Burgupally Gram Panchayat, represented by its Panchayat Secretary.
The supplied drawing material does not establish plot-by-plot dimensions, layout orientation, road-by-road widths beyond the stated 33'-0"road condition concerning an existing road, or the final as-built arrangement. The approval requires roads to be opened for access to neighbouring sites and open space and road land to be handed over to the Gram Panchayat by registered gift deed before release of the final layout.
The RERA project record describes plots, not residential units in a building. It supplies a total of 261 plots in the draft layout approval, but no RERA-filed plot-size bands, plot-wise inventory, booked/available count or saleable-area schedule. RERA filing
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| Plots | 261 in the draft layout approval | Not supplied | Not supplied | Not supplied | Not applicable | Not supplied |
Three drawings are recorded as pending scan processing; none has a software-measured area. Accordingly, no plot or home dimensions can be reported as software-measured from those drawings. Floor plans
The draft layout approval identifies a 26.73 % road-area allocation and requires roads to be opened for neighbouring-site access. The supplied evidence does not state a sanctioned vehicle-parking count, visitor or accessible parking provision, parking allotment arrangements, or a parking layout.
A vendor listing mentions “Open Car Parking,” but this is a third-party claim and is not established as a sanctioned or delivered facility in the supplied layout approval. Promoter website
The draft layout approval specifies development works including side drains, nala channelization, avenue plantation, rainwater-harvesting pits, street lighting, electricity facilities, a sewerage-disposal system and protected water supply. These are approval conditions or required works, not evidence that the facilities have been completed.
The RERA filing’s amenity-progress entries are shown below. Percentages are filed progress figures; the data does not independently verify completion.
| Description / size | Open-space allocation in draft approval: Ac. 2.53 Cents; 12245.20 Sq. Yds (10.00 %) |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | RERA amenity record: available “YES,” 10%; not independently verified RERA amenities |
| Description / size | Approval requires rain water harvesting pits |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | RERA amenity record: available “YES,” 15%; not independently verified RERA amenities |
| Description / size | Required in the draft approval |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | RERA amenity record: available “YES,” 10%; not independently verified RERA amenities |
| Description / size | Draft approval allocates road area Ac. 6.86 Cents; 33202.40 Sq. Yds. (26.73 %) |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | RERA amenity record: 0% RERA amenities |
| Description / size | Draft approval specifies protected water supply |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | RERA amenity record: available “YES,” 10%; not independently verified RERA amenities |
| Description / size | Draft approval specifies a sewerage disposal system |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | RERA entries for “Sewerage (Chamber, Lines, Septic Tank, STP)” and “Treatment And Disposal Of Sewage And Sullage Water”: 0% RERA amenities |
| Description / size | Approval requires side drains and nala channelization |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | RERA amenity record: 0% RERA amenities |
| Description / size | No size or facility detail supplied |
|---|---|
| Evidence source | RERA amenities |
| Declared progress / verified status | RERA amenity record: 0% RERA amenities |
The vendor’s amenity list includes facilities such as a banquet hall, courts, gym, swimming pool and guest house; these are third-party-listed features and are not established as part of the supplied sanctioned layout record. Promoter website
The draft layout approval lists protected water supply, electricity facilities, a sewerage-disposal system, side drains, nala channelization, rainwater-harvesting pits and street lighting as development works. It does not give capacities, technical designs, delivery status or independent commissioning evidence.
The RERA amenity-progress record shows water supply at 10%, rainwater conservation/harvesting at 15%, and street lighting at 10%. Sewerage, sewage and sullage treatment/disposal, storm-water drains, solid-waste management, energy management, fire protection, and electrical meter room/sub-station/receiving station are each recorded at 0%. These are filed progress figures rather than an independent inspection or a determination of statutory compliance. RERA amenities
No supplied project-specific evidence establishes water-storage or treatment capacity, sewage-treatment plant capacity, electrical backup, fire equipment or clearances, security systems, accessibility arrangements, or waste segregation facilities. A vendor listing mentions a sewage treatment plant and security-related amenities, but those claims are not confirmed by the supplied layout approval or RERA progress record. Promoter website
The RERA project identity places Panchavati in Burgupally Gram Panchyat, Ranga Reddy district, PIN 501101. The layout approval identifies Burgupally village, Machanpally (M), and Vikarabad District. The supplied records do not establish a named approach road or public-transport connection. RERA record
A supplied location record identifies the Financial District (Nanakramguda) at 1.2 km from the cadastral parcel-centroid location. Location record The remaining connectivity statement about nearby facilities is a vendor claim without measured distances. Promoter website
The registered promoter is JP DEVELOPERS, identified in the project filing as a partnership. The supplied record names Janardhan Kompally and Narasimha N V L Reddy as partners and Pradeep Kumar Atoori as authorized signatory. The promoter address is recorded as 1st Floor, Shiva Nagar, Machanpally Village, Burgupally Gram Panchyat, Ranga Reddy, 501101. RERA record RERA filing Parties record
The RERA registration certificate names Jp Developers, registration P02400001495, and gives validity from 27/12/2019 to 02/11/2020, with no extension recorded in the supplied certificate. The Form B affidavit, dated 21-09-2019, is a promoter-authorized declaration stating a completion period of 2.5 Years from the date of commencement. This is a declaration, not independent confirmation of completion.
The supplied record does not establish current construction status, final layout release, or the existence or scope of any occupancy or completion certificate. Document index RERA amenities
| Record | Supplied evidence |
|---|---|
| TG-RERA registration | Form “C” registration certificate for Panchavati, P02400001495, under section 5; issued 27/12/2019, valid through 02/11/2020; no extension recorded in the certificate |
| Principal layout approval | Director of Town and Country Planning, Draft-TLP.No.111/2018/H; letter Lr.Roc.No. 3242/2018/H, date printed 2--11-2018; approval delegated to Burgupally Gram Panchayat |
| Other approval identifiers in the layout record | Gram Panchayat letter Lr.No.GP/, 01/2018, dated 07/06/2018; Circular Memo 1637/2018/P, dated 18-05-2018 and 19-05-2018 |
| Layout / land-use information | Draft approval records 261 plots; land-use allocation and approval conditions are set out in the project record |
| Form B declaration | Promoter-authorized affidavit dated 21-09-2019, including declared title, encumbrance and completion-period statements |
| Completion / occupancy records | No completion or occupancy certificate is included in the supplied documents Document index |
| Other filed project materials | Encumbrance statement (doc 79349), legal title report (doc 79348), registration certificate (doc REGCERT-11644) and blank-form Agreement for Sale (doc 79350) are listed in the project evidence Document index |
The draft layout approval states that its permission is not proof of land title, requires completion of development works and provides for a final layout approval. The supplied documents do not establish that the final layout approval or completion certificate was issued.
Project identity
Registered project name: Panchavati
Project type: Plotted development / plotted layout
Phase / registered portion: Phase not separately identified; TG-RERA registration is for Panchavati
TG-RERA registration: P02400001495; issued 27/12/2019 and valid through 02/11/2020. The certificate records no extension
Registered promoter: JP DEVELOPERS (certificate styling: “Jp Developers”); partnership
RERA status in supplied record: Registration certificate issued; its stated validity period has ended. Current registration status is not established by the supplied record
Land and geographic identity
Locality / revenue village: Burgupally Gram Panchyat in the RERA filing; the layout approval identifies Burgupally village and Burgupally Gram Panchayat
Mandal: Not disclosed in the RERA identity fields. The layout approval names Machanpally (M)
District: Ranga Reddy in the RERA project record; the layout approval states Vikarabad District
PIN: 501101 in the project header and registration certificate
Survey numbers / subdivisions: 24/A, 24/AA, 24E, 25A, 25AA and 25E in the RERA project record; the layout approval writes these as 24/A, 24/AA, 24/E, 25/A, 25/AA and 25/E
Site extent in project filing: Total 103842.34 sq.mts; affected area 1456.87 sq.mts; net area 102385.47 sq.mts
Extent stated in layout approval: Total layout area Ac. 25.66 Cents; 124194.40 Sq. Yds.; net layout area Ac. 25.30 Cents; 122452.00.Sq. Yds
Boundaries recorded in project filing: East: Nala and Neighbours Land; West: Railway Track; North: Land belongs to Harsha Vardhan Reddy and Others; South: Land belongs to Patti Prakasham
Development identity
Sanctioning authority: Director of Town and Country Planning; approval delegated to Burgupally Gram Panchayat
Principal layout approval: Draft-TLP.No.111/2018/H; approval letter number Lr.Roc.No. 3242/2018/H, dated as printed 2--11-2018
RERA-filed plan reference: TLP.No.111/201/H
Approved layout scale: 261 plots in the draft layout approval
Land-use split stated in draft approval: Total layout area Ac. 25.66 Cents; 124194.40 Sq. Yds.; Nala Area Ac. 0.36Cents; 1742.40 Sq Yds.; Net Layout Area Ac. 25.30 Cents; 122452.00.Sq. Yds; open space Ac. 2.53 Cents; 12245.20 Sq. Yds (10.00 %); road area Ac. 6.86 Cents; 33202.40 Sq. Yds. (26.73 %); plotted area Ac. 16.234 Cents; 78572.56 Sq. Yds (63.27 %); mortgage area Ac.2.44 Cents; 11809.60 Sq. Yds. (15.03 %)
Approved built-up area / buildings and floors: Not applicable to the filed plotted-layout description; no building count, floor configuration or approved building built-up area is supplied for this layout
Offering and status
RERA-identified offering: Plots; the project’s RERA filing identifies a plotted development
Plot count: 261 plots in the draft layout approval
RERA-filed plot size range / inventory: Not supplied in the available RERA project data
Marketing-described plot size: “plot 1800 - 3600 sq.ft (167.23 - 334.45 sq.m)”—a vendor/third-party listing, not a RERA-filed figure
Construction / development stage: RERA amenity entries report water supply, green strip/park, street lighting and rainwater harvesting at 10%, 10%, 10% and 15%, respectively; several other listed infrastructure items are shown at 0%. These are filed progress figures, not an independent site inspection
Completion deadline: RERA header gives proposed completion 02/11/2020; the registration certificate was valid through the same date
Occupancy / completion certificate: No occupancy or completion certificate is present in the supplied project documents. The plotted-layout approval calls for completion of required works and final layout approval
Panchavati is registered as a plotted-development project by JP DEVELOPERS, covering the survey subdivisions 24/A, 24/AA, 24E, 25A, 25AA and 25E. The filed project details identify Burgupally Gram Panchyat, Ranga Reddy district and PIN 501101; the draft layout approval describes the site as Burgupally village under Machanpally (M).
The layout approval describes a scheme of 261 plots, with land allocated to plotted area, roads, open space, a nala area and plots reserved as mortgage security to the Gram Panchayat. Its conditions require development works and a subsequent final layout approval; the document expressly says permission to develop the land is not proof of title.
The RERA registration certificate ran from 27/12/2019 to 02/11/2020 and records no extension. The supplied record does not establish the current on-site condition, whether all layout works are complete, whether final layout approval was issued, or whether a completion certificate was obtained. The percentages entered for selected infrastructure components are promoter-filed progress information, not independently verified construction progress.
This is a plotted layout, not a building or apartment scheme in the supplied project record. The RERA-filed land details state total area 103842.34 sq.mts, affected area 1456.87 sq.mts, and net area 102385.47 sq.mts. The draft layout approval separately describes total and net layout extents in acres and square yards.
The draft approval allocates 10.00 % of the layout to open space, 26.73 % to roads and 63.27 % to plotted area. It also identifies Ac. 0.36Cents; 1742.40 Sq Yds. as Nala Area and Ac.2.44 Cents; 11809.60 Sq. Yds. as mortgage area. Plots 135 TO 174 are specified for mortgage to Burgupally Gram Panchayat, represented by its Panchayat Secretary.
The supplied drawing material does not establish plot-by-plot dimensions, layout orientation, road-by-road widths beyond the stated 33'-0"road condition concerning an existing road, or the final as-built arrangement. The approval requires roads to be opened for access to neighbouring sites and open space and road land to be handed over to the Gram Panchayat by registered gift deed before release of the final layout.
The RERA project record describes plots, not residential units in a building. It supplies a total of 261 plots in the draft layout approval, but no RERA-filed plot-size bands, plot-wise inventory, booked/available count or saleable-area schedule.
| Configuration | Units | Booked | Available | RERA saleable area | Measured carpet area | Loading (if supplied) |
|---|---|---|---|---|---|---|
| Plots | 261 in the draft layout approval | Not supplied | Not supplied | Not supplied | Not applicable | Not supplied |
Three drawings are recorded as pending scan processing; none has a software-measured area. Accordingly, no plot or home dimensions can be reported as software-measured from those drawings.
The draft layout approval identifies a 26.73 % road-area allocation and requires roads to be opened for neighbouring-site access. The supplied evidence does not state a sanctioned vehicle-parking count, visitor or accessible parking provision, parking allotment arrangements, or a parking layout.
A vendor listing mentions “Open Car Parking,” but this is a third-party claim and is not established as a sanctioned or delivered facility in the supplied layout approval.
The draft layout approval specifies development works including side drains, nala channelization, avenue plantation, rainwater-harvesting pits, street lighting, electricity facilities, a sewerage-disposal system and protected water supply. These are approval conditions or required works, not evidence that the facilities have been completed.
The RERA filing’s amenity-progress entries are shown below. Percentages are filed progress figures; the data does not independently verify completion.
| Facility | Description / size | Evidence source | Declared progress / verified status |
|---|---|---|---|
| Green Strip/TOT LOT/Park | Open-space allocation in draft approval: Ac. 2.53 Cents; 12245.20 Sq. Yds (10.00 %) | RERA amenity record: available “YES,” 10%; not independently verified | |
| Water Conservation, Rain water Harvesting | Approval requires rain water harvesting pits | RERA amenity record: available “YES,” 15%; not independently verified | |
| Street Lighting | Required in the draft approval | RERA amenity record: available “YES,” 10%; not independently verified | |
| Internal Roads & Footpaths | Draft approval allocates road area Ac. 6.86 Cents; 33202.40 Sq. Yds. (26.73 %) | RERA amenity record: 0% | |
| Water Supply | Draft approval specifies protected water supply | RERA amenity record: available “YES,” 10%; not independently verified | |
| Sewerage / sewage disposal | Draft approval specifies a sewerage disposal system | RERA entries for “Sewerage (Chamber, Lines, Septic Tank, STP)” and “Treatment And Disposal Of Sewage And Sullage Water”: 0% | |
| Storm-water drains | Approval requires side drains and nala channelization | RERA amenity record: 0% | |
| Community buildings | No size or facility detail supplied | RERA amenity record: 0% |
The vendor’s amenity list includes facilities such as a banquet hall, courts, gym, swimming pool and guest house; these are third-party-listed features and are not established as part of the supplied sanctioned layout record.
The draft layout approval lists protected water supply, electricity facilities, a sewerage-disposal system, side drains, nala channelization, rainwater-harvesting pits and street lighting as development works. It does not give capacities, technical designs, delivery status or independent commissioning evidence.
The RERA amenity-progress record shows water supply at 10%, rainwater conservation/harvesting at 15%, and street lighting at 10%. Sewerage, sewage and sullage treatment/disposal, storm-water drains, solid-waste management, energy management, fire protection, and electrical meter room/sub-station/receiving station are each recorded at 0%. These are filed progress figures rather than an independent inspection or a determination of statutory compliance.
No supplied project-specific evidence establishes water-storage or treatment capacity, sewage-treatment plant capacity, electrical backup, fire equipment or clearances, security systems, accessibility arrangements, or waste segregation facilities. A vendor listing mentions a sewage treatment plant and security-related amenities, but those claims are not confirmed by the supplied layout approval or RERA progress record.
The RERA project identity places Panchavati in Burgupally Gram Panchyat, Ranga Reddy district, PIN 501101. The layout approval identifies Burgupally village, Machanpally (M), and Vikarabad District. The supplied records do not establish a named approach road or public-transport connection.
A supplied location record identifies the Financial District (Nanakramguda) at 1.2 km from the cadastral parcel-centroid location. The remaining connectivity statement about nearby facilities is a vendor claim without measured distances.
The registered promoter is JP DEVELOPERS, identified in the project filing as a partnership. The supplied record names Janardhan Kompally and Narasimha N V L Reddy as partners and Pradeep Kumar Atoori as authorized signatory. The promoter address is recorded as 1st Floor, Shiva Nagar, Machanpally Village, Burgupally Gram Panchyat, Ranga Reddy, 501101.
The RERA registration certificate names Jp Developers, registration P02400001495, and gives validity from 27/12/2019 to 02/11/2020, with no extension recorded in the supplied certificate. The Form B affidavit, dated 21-09-2019, is a promoter-authorized declaration stating a completion period of 2.5 Years from the date of commencement. This is a declaration, not independent confirmation of completion.
The supplied record does not establish current construction status, final layout release, or the existence or scope of any occupancy or completion certificate.
TG-RERA registration: Form “C” registration certificate for Panchavati, P02400001495, under section 5; issued 27/12/2019, valid through 02/11/2020; no extension recorded in the certificate
Principal layout approval: Director of Town and Country Planning, Draft-TLP.No.111/2018/H; letter Lr.Roc.No. 3242/2018/H, date printed 2--11-2018; approval delegated to Burgupally Gram Panchayat
Other approval identifiers in the layout record: Gram Panchayat letter Lr.No.GP/, 01/2018, dated 07/06/2018; Circular Memo 1637/2018/P, dated 18-05-2018 and 19-05-2018
Layout / land-use information: Draft approval records 261 plots; land-use allocation and approval conditions are set out in the project record
Form B declaration: Promoter-authorized affidavit dated 21-09-2019, including declared title, encumbrance and completion-period statements
Completion / occupancy records: No completion or occupancy certificate is included in the supplied documents
Other filed project materials: Encumbrance statement (doc 79349), legal title report (doc 79348), registration certificate (doc REGCERT-11644) and blank-form Agreement for Sale (doc 79350) are listed in the project evidence
The draft layout approval states that its permission is not proof of land title, requires completion of development works and provides for a final layout approval. The supplied documents do not establish that the final layout approval or completion certificate was issued.
Yes. Panchavati is registered with the Telangana Real Estate Regulatory Authority as P02400001495; the registration status is New Project.
The promoter named in the RERA registration is JP DEVELOPERS.
Panchavati is in Burgupally Gram Panchyat, Rangareddy, Telangana (501101).
The promoter's proposed date of completion filed with RERA is 02/11/2020. This is the promoter's declaration, not a guarantee.