Dimond City Phase - II
DIMOND CITY PHASE - II is a plotted development in Narsapuram, Valigonda Mandal, Yadadri Bhuvanagiri District, developed by the registered promoter M/s SRI SIDDI VINAYAKA DEVELOPERS. The registered site area is 44,616.59 sq. m, and the draft layout approval specifies 138 plots; plot configurations are not stated. The project is registered under TG-RERA number P02000005391, and the promoter’s completion undertaking is 02.10.2024.
More from Sri Siddi Vinayaka Developers · 8 projects →
At a glance
- RERA registration
- P02000005391
- Registration valid
- 29/11/2022 to 02/10/2024; the certificate states validity unless extended by the Authority. It records no extension.
- Promoter
- M/s SRI SIDDI VINAYAKA DEVELOPERS; partnership
- Site area
- 44,616.59 sq. m; the RERA filing labels this as both total and net area, with 0 sq. m affected by road widening/FTL of tanks/nala widening.
- Building permit
- Director of Town and Country Planning (DTCP); the letter says delegated to Narsapur Gram Panchayat.
- Saleable area
- Not disclosed in the supplied RERA records.
- Booked / available
- Not supplied.
- Construction stage
- RERA filing reports 80% completeness; this is a filed progress figure, not an independent site inspection.
The full project file
Description
Dimond City Phase II is a plotted development on 44,616.59 sq m of land. It is filed as a new project, with proposed completion on 2 October 2024.
- Project type
- Plotted DevelopmentRERA filing
- Land area
- 44616.59 sq mRERA filing
- Possession
- 02/10/2024RERA filing
- Status
- New ProjectRERA filing
Amenities
The disclosed amenities include a park or green strip, alongside internal roads, street lighting and rainwater harvesting infrastructure.
- Green Strip/TOT LOT/Park
Location & connectivity
The project is in Narsapur, PIN 508112, in Valigonda mandal, Yadadri Bhuvanagiri district.
Promoter
The promoter is M/s SRI SIDDI VINAYAKA DEVELOPERS, a partnership; its official website is ssvd.co.in. The promoter has 7 other registered projects, and the named architect is BASITH ALI.
Additional details
Sources & web results
- DIMOND CITY PHASE - II Ranga Reddyaurumproptech.in
Public RERA registration record
Telangana RERA, as filed by the promoter.
- Registered name
- DIMOND CITY PHASE - II
- Developer / Promoter
- M/s SRI SIDDI VINAYAKA DEVELOPERS
- Project type
- Plotted Development
- RERA Registration No.
- P02000005391
- Registration Status
- New Project
- Approved on
- 03/10/2022
- Proposed completion
- 02/10/2024
- Approving authority
- DTCP
- Plan approval no.
- TLP.No.303/2022/H
- Total site area
- 44,617 sq m (11.0 acres)
- Approved built-up area
- 24,018 sq m (5.9 acres)
- Locality
- NARSAPUR, Narsapuram
- Mandal
- Valigonda
- District
- Yadadri Bhuvanagiri
- PIN code
- 508112
- Documents on File
- 15
Frequently asked questions
Is DIMOND CITY PHASE - II registered with Telangana RERA?
Yes. DIMOND CITY PHASE - II is registered with the Telangana Real Estate Regulatory Authority as P02000005391; the registration status is New Project.
Who is the developer of DIMOND CITY PHASE - II?
The promoter named in the RERA registration is M/s SRI SIDDI VINAYAKA DEVELOPERS.
Where is DIMOND CITY PHASE - II located?
DIMOND CITY PHASE - II is in NARSAPUR, Narsapuram, Valigonda, Yadadri Bhuvanagiri, Telangana (508112).
When will DIMOND CITY PHASE - II be completed?
The promoter's proposed date of completion filed with RERA is 02/10/2024. This is the promoter's declaration, not a guarantee.